2018-05-08

Environmental Impact Assessment of the 43#~45# Liquid Bulk Berth Project of Sigangchi, Xugang Port Area, Lianyungang Port (First Time) Publicity

In order to fully understand the opinions of different parties on the construction of the 43#~45# liquid bulk berth project in Sigangchi, Xujing Port, Lianyungang Port , and to better do environmental protection work, according to the Interim Measures for Public Participation in Environmental Impact Assessment, The relevant spirit of the Circular of the Oceanic Administration on the Relevant Issues Concerning Public Participation in the Environmental Impact Assessment Report for Offshore Engineering Construction Projects, we now announced on the environmental impact assessment of the project, and the information on environmental impact assessment is disclosed to the public and public comments are sought.

1. Overview of the project construction

The proposed 43#~45# liquid bulk berth project of Sigang Pool in Xujing Port Area of Lianyungang Port is located at the root of Sigangchi, Xujing Port Area, Lianyungang Port. The project plans to build a new liquid chemical terminal and corresponding supporting facilities, including 2 50,000-ton liquid chemical berths ( designed for hydraulic structures according to 100,000- ton ships) and 1 30,000- ton liquid chemical berth . The project mainly meets the requirements of satellite petrochemical throughput. The annual designed throughput is 5.47 million tons. The loading and unloading goods are low-temperature ethane, propane, butane, ethylene, propylene, butylene and other liquefied hydrocarbons and ethylene glycol, butanol and octanol. Liquid chemical products such as methyl methacrylate, including 4.3 million tons of imported goods and 1.17 million tons of exported goods.

The construction period of the project is 12 months, with a total investment of about 479.27 million yuan.

2. Construction company: Lianyungang Hexing Petrochemical Terminal Co., Ltd.

Contact: Zhang Yuanling

Contact: 13957398535 Fax: 051882106616

Email: zhangyuanling@weixing.com.cn

3. Environmental Impact Assessment Agency: TIWTE Environmental Technology Development (Tianjin) Co., Ltd.

Address: Marine Resources Center, Tianke Institute, No. 2718 , No. 2 Road , Xingang, Tanggu, Tianjin , China ( 300456 )

Contact: Shou Youping

Tel: 022-59812345-6324 Fax: 022-59812389

Email: zyhj@vip.163.com

4. Main work contents of environmental impact assessment

The evaluation unit will, in accordance with the requirements of the Environmental Impact Assessment Law of the People's Republic of China and other relevant countries and Jiangsu Province, with the guidance of the environmental assessment guidelines, combined with the characteristics of the project, make full use of the existing data, supplement the necessary status monitoring, and combine Engineering design and forecasting data, predicting and evaluating the impact of the construction period and operation period of the project on the water environment and ecological environment of the project area, and proposing environmental protection measures, environmental management and environmental monitoring plans from a reasonable and technically feasible perspective.

5. The main matters of public consultation

Whether support for construction projects; impact of project construction on your life; opinions on project implementation that may cause pollution; impact of project construction on local economy; recommendations and requirements for project construction.

6. The main way for the public to make comments

Telephone contact with the construction company or the EIA unit; send a letter or mail to the construction unit or the EIA unit; directly to the construction unit or the EIA unit to respond.

7. Other

The request for comment is within 10 working days from May 8 to May 21, 2018.